SpaceX · Arizona · 23 Nov 2026

Arizona's attorney general wants Cochise County to hold off on SpaceX's 6 GW campus vote

Attorney General Kris Mayes wrote to the Cochise County Planning and Zoning Commission on Thursday, 19 Nov, asking it to delay its 9 Dec vote on SpaceX's special use permit until state and federal regulators have reviewed the project. She has also called a town hall in Cochise for 3 Dec. This is a request, not a ruling. I found no public change to the commission's schedule and no public response from SpaceX as of Monday afternoon ET.

From Alex RSpaceX · News & analysis

The editor holds Tesla and SpaceX shares. Supercharged Daily is independent and not affiliated with SpaceX. Nothing here is financial advice.

Flat, dry lakebed of the Willcox Playa in Cochise County, Arizona, with mountains on the horizon
The Willcox Playa, Arizona's largest dry lake. The attorney general's letter says the proposed 747-acre campus sits immediately next to it. Photo: Bureau of Land Management Arizona, public domain, via Wikimedia Commons.
DISPATCH About 5 min read
On this page

What Mayes asked for

The five-page letter, dated 19 Nov and addressed to Chairman Kim DePew and the commission, concerns special use permit SU26-22 from Tombstone Resources, LLC, which the letter refers to as SpaceX. It covers a data center operation of 1.5 GW at first and 6 GW at full build-out. I covered the application itself earlier this month.

Mayes asks the commission to delay the 9 Dec vote so that the county "does not begin authorizing the project" before the relevant state and federal regulators have vetted it. If the commission goes ahead anyway, she lists conditions: the permit should not take effect until every state and federal authorization is in hand, building permits should wait on the same thing, the full 6 GW should be assessed at once rather than phase by phase, and there should be more public meetings, including one in Willcox.

In the press release that went out with the letter, Mayes said questions about energy reliability, water use, emergency response, traffic and the effect on nearby communities must be "fully examined by the appropriate state and federal agencies before any local approval moves forward." Her office says it will also seek more information from SpaceX. The letter was copied to the county supervisors, the members of the Arizona Corporation Commission and Michael Smith of Tombstone Resources.

The numbers she pulled from the application

Most of the figures in the letter come from SpaceX's own application, which Mayes calls a "mere 55-page application (already amended several times)." It was first filed on 30 Oct. Here they are side by side with a little arithmetic of mine.

ItemIn the letterFor scale (my math unless noted)
Power at full build-out6 GW"Nearly 20 percent of Arizona's total power generating capacity," per the letter, citing EIA
Backup batteries24 GWh of lithium-ion phosphate batteriesThe letter puts it at 6,150 Tesla Megapacks, about 3.9 MWh each
BuildingsNine at 493,000 sq ft eachAbout 4.4 million sq ft in total
Site747 acres next to the Willcox PlayaOutside any fire district, per the letter
Water7 to 10 acre-feet a year, dry cooledAbout 2.3 to 3.3 million gallons a year
Grid spending$3.6 billion, as stated in the proposalA developer figure, not a utility filing
Peak construction5,500 workers, four phases from as early as March 2027A plan, not a hiring commitment

Figures from the Arizona Attorney General's 19 Nov 2026 letter, which quotes SpaceX's SU26-22 application. The total floor area and gallon conversion are my math.

Her argument on water is that the 7 to 10 acre-feet figure covers staff use and leaves out the water used to generate 6 GW of electricity, in a basin that sits inside the Willcox Active Management Area. The letter also raises possible interference with testing at Fort Huachuca's U.S. Army Electronic Proving Ground.

Dates to watch

The town hall is on Thursday, 3 Dec, from 7:30pm to 9pm ET (4:30pm to 6pm PT), which is 5:30pm to 7pm in Arizona, at the Cochise Elementary School gymnasium, 5025 North Bowie Avenue, Cochise, per the attorney general's official flyer. The letter puts the commission's vote on 9 Dec. The application file is on the county's website.

My read

A state attorney general has no vote on a county land-use permit, so this is pressure, and it lands two weeks before the commission meets. Some of what she asks for would hit SpaceX's timeline hard. Tying the permit's effective date to every state and federal sign-off could delay construction that the application plans to start as early as March 2027. Other parts look easy to meet. A Willcox meeting and a single 6 GW impact study cost time, not the project. As a shareholder I want this campus built, and I'd still rather see SpaceX answer the water and power questions in public before 9 Dec than win the vote and fight about it afterwards. Tell me below: should Cochise County vote on 9 Dec, or wait?

— Alex R

Sources: Arizona Attorney General letter to the Cochise County Planning and Zoning Commission, 19 Nov 2026; Arizona Attorney General press release, 19 Nov 2026; town hall flyer; Cochise County SU26-22 application file. Floor area and water conversions are my math. Photo: BLM Arizona, public domain.